[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254153,838,2,"多选题","专项施工方案的技术先进性比较，主要指（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","比较不同方案的技术水平",true,{"key":16,"text":17,"correct":14},"B","比较不同方案的技术创新程度",{"key":19,"text":20,"correct":14},"C","比较不同方案的技术效率",{"key":22,"text":23,"correct":14},"D","比较不同方案实施的安全可靠性",{"key":25,"text":26,"correct":27},"E","比较不同方案的社会效益（如资源节约、污染降低）",false,"ABCD","专项施工方案的技术先进性比较，主要指：比较不同方案的技术水平、比较不同方案的技术创新程度、比较不同方案的技术效率、比较不同方案实施的安全可靠性。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]