[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254121":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254121,838,2,"多选题","汽车式起重机，在吊装前的基础处理做法正确选项的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","必须对吊车站立位置的地基进行平整和压实，按规定进行沉降预压试验",true,{"key":16,"text":17,"correct":18},"B","必须对吊车站立位置的地基进行平整和压实，但不需要沉降预压试验",false,{"key":20,"text":21,"correct":14},"C","在复杂地基上吊装重型设备，应请专业人员对基础进行专门设计",{"key":23,"text":24,"correct":18},"D","在复杂地基上吊装重型设备，无须请专业人员对基础进行专门设计",{"key":26,"text":27,"correct":14},"E","在复杂地基上吊装重型设备，基础验收时要进行沉降预压试验","ACE","汽车式起重机，在吊装前的基础处理做法正确选项的有：必须对吊车站立位置的地基进行平整和压实，按规定进行沉降预压试验；在复杂地基上吊装重型设备，应请专业人员对基础进行专门设计；在复杂地基上吊装重型设备，基础验收时要进行沉降预压试验。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]