[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254111":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254111,838,2,"多选题","管道试压的步骤有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","接好试压泵",true,{"key":16,"text":17,"correct":18},"B","打开入口总阀和所有泄水阀门和低处放水阀门",false,{"key":20,"text":21,"correct":14},"C","打开系统内的各支路及主干管的阀门",{"key":23,"text":24,"correct":14},"D","打开系统最高处的排气阀门",{"key":26,"text":27,"correct":14},"E","关闭入口总阀和所有泄水阀门和低处放水阀门","ACDE","管道试压的步骤：接好试压泵；关闭入口总阀和所有泄水阀门和低处放水阀门；打开系统内的各支路及主干管上的阀门；打开系统最高处的排气阀门；打开试压用水源阀门，系统充水等。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]