[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254105":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254105,838,2,"多选题","下列属于管道试压的组织步骤的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","接好试压泵",true,{"key":16,"text":17,"correct":14},"B","打开系统最高处的排气阀门",{"key":19,"text":20,"correct":14},"C","满水后排净空气，并将排气阀关闭",{"key":22,"text":23,"correct":14},"D","进行满水情况下全面检查，如有渗漏及时处理，处理好后才能加压",{"key":25,"text":26,"correct":27},"E","做好防冻措施",false,"ABCD","管道试压的组织步骤的是：（1）接好试压泵。（2）关闭人口总阀和所有泄水阀及低处放水阀门。（3）打开系统内各支路及主干管上的阀门。（4）打开系统最高处的排气阀门。（5）打开试压用水源阀门，系统充水。（6）满水后排净空气，并将排气阀关闭。（7）进行满水情况下全面检查，如有渗漏及时处理，处理好后才能加压。（8）加压试验并检查，直至全面合格。加压应缓慢升压至试验压力。（9）拆除试压泵、关闭试压用水源、泄放系统内试压用水，直至排净。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]