[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1254069,838,1,"单选题","（ ）是表明电气工程的固定方式、电能输送、分配控制关系和设备运行的图纸。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系统图",true,{"key":16,"text":17,"correct":18},"B","平面图",false,{"key":20,"text":21,"correct":18},"C","安装详图",{"key":23,"text":24,"correct":18},"D","电气原理图","系统图是表明电气工程的固定方式、电能输送、分配控制关系和设备运行的图纸。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]