[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254013":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":24},1254013,838,1,"单选题","专项施工方案编制后要经过（ ）签字确认后实施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位质量负责人和总监理工程师",false,{"key":16,"text":17,"correct":14},"B","施工单位技术负责人和监理工程师",{"key":19,"text":20,"correct":21},"C","施工单位技术负责人和总监理工程师",true,{"key":23,"text":13,"correct":14},"D","专项施工方案编制后要经过施工单位技术负责人、总监理工程师签字确认后实施。",{"id":6,"name":26,"category":27,"favorite":28},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]