[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1254009,838,1,"单选题","备案机关发现建设单位在竣工验收过程中有违反国家有关建设工程质量管理规定行为的，应在收讫竣工验收备案文件（ ）日内，责令停止使用，重新组织竣工验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","10",{"key":23,"text":24,"correct":14},"D","8","备案机关发现建设单位在竣工验收过程中有违反国家有关建设工程质量管理规定行为的，应在收讫竣工验收备案文件15日内，责令停止使用，重新组织竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]