[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253996":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253996,838,1,"单选题","不属于编制专项工程方案的工程有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","其他危险性较大的工程",false,{"key":16,"text":17,"correct":14},"B","起重吊装工程",{"key":19,"text":20,"correct":14},"C","拆除爆破工程",{"key":22,"text":23,"correct":24},"D","高大模板工程",true,"编制专项工程方案的工程有：基坑支护与降水工程；土方开挖工程；模板工程；起重吊装工程；脚手架工程；拆除爆破工程；其他危险性较大的工程。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]