[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253985,838,1,"单选题","以下信息中属于生产信息的有（ ）。①改进的办法②重大决策信息③施工进度计划④劳动力流动⑤材料消耗",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②③",false,{"key":16,"text":17,"correct":14},"B","①②④⑤",{"key":19,"text":20,"correct":21},"C","③⑤",true,{"key":23,"text":24,"correct":14},"D","①②④","根据第11章工程信息资料处理可知：属于生产信息的有：施工进度计划、材料消耗。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]