[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253984,838,1,"单选题","建设工程项目的实施需要人力资源和物质资源，应认识到（ ）资源也是项目实施的重要资源之一。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本",false,{"key":16,"text":17,"correct":14},"B","质量",{"key":19,"text":20,"correct":21},"C","信息",true,{"key":23,"text":24,"correct":14},"D","合同","建设工程项目的实施需要人力资源和物质资源，应认识到信息资源也是项目实施的重要资源之一。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]