[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253953,838,1,"单选题","以下哪个不属于关键过程：（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","锅炉安装",false,{"key":16,"text":17,"correct":14},"B","变压器安装",{"key":19,"text":20,"correct":14},"C","电缆线路布设",{"key":22,"text":23,"correct":24},"D","洁具安装",true,"关键过程一般包括：测量放线、锅炉安装、变压器安装、成套配柜（盘）及动力开关柜安装、电缆线路布设、大型设备吊装、系统无负荷试运行、大设备现场安装、超长\u002F超重设备运输、大型设备现场组装、高压设备或高压管道耐压严密性试验、电气\u002F通风\u002F仪表系统调试、烘\u002F煮炉等。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]