[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253952,838,1,"单选题","在质量管理的PDCA循环中，明确质量目标并制订实现质量目标的行动方案属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划",true,{"key":16,"text":17,"correct":18},"B","实施",false,{"key":20,"text":21,"correct":18},"C","检查",{"key":23,"text":24,"correct":18},"D","处置","在质量管理的PDCA循环中，明确质量目标并制订实现质量目标的行动方案属于计划。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]