[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253903,838,1,"单选题","已知某安装工程，分项分部工程量清单计价1770万元，措施项目清单计价51.34万元，其他项目清单计价100万元，规费80万元，税金68.25万元，则其招标控制价应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2069.59万元",true,{"key":16,"text":17,"correct":18},"B","1821.43万元",false,{"key":20,"text":21,"correct":18},"C","1838.25万元",{"key":23,"text":24,"correct":18},"D","1950万元","1770+51.34+100+80+68.25=2069.59万元",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]