[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253893":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253893,838,1,"单选题","根据有关规定，在居民密集区进行强噪声施工作业时，夜间作业时间不得超过（ ），施工现场早晨作业时间不得早于6时。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20时",false,{"key":16,"text":17,"correct":14},"B","21时",{"key":19,"text":20,"correct":21},"C","22时",true,{"key":23,"text":24,"correct":14},"D","23时","根据有关规定，在居民密集区进行强噪声施工作业时，夜间作业时间不得超过22时，施工现场早晨作业时间不得早于6时。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]