[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253843,838,1,"单选题","变动成本是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","指在一定期间和一定的工程量范围内，成本额不受工程量增减变动的影响而相对固定的成本",false,{"key":16,"text":17,"correct":14},"B","指为施工准备、组织管理施工作业而发生的费用支出，这些设计施工生产必须发生的",{"key":19,"text":20,"correct":14},"C","施工项目承建所承包工程实际发生的各项生产费用的总和",{"key":22,"text":23,"correct":24},"D","指成本发生总额随着工程量的增减变动而成正比例变动的费用",true,"变动成本是指成本发生总额随着工程量的增减变动而成正比例变动的费用，如材料费和人工费。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]