[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253838,838,1,"单选题","确定施工成本偏差的严重性和偏差产生的原因，是施工成本控制过程中（ ）阶段要解决的问题。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","比较",false,{"key":16,"text":17,"correct":18},"B","分析",true,{"key":20,"text":21,"correct":14},"C","预测",{"key":23,"text":24,"correct":14},"D","纠偏","确定施工成本偏差的严重性和偏差产生的原因，是施工成本控制过程中分析阶段要解决的问题。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]