[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253835,838,1,"单选题","固定成本是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","指在一定期间和一定的工程量范围内，成本额不受工程量增减变动的影响而相对固定的成本",true,{"key":16,"text":17,"correct":18},"B","指为施工准备、组织管理施工作业而发生的费用支出，这些设计施工生产必须发生的",false,{"key":20,"text":21,"correct":18},"C","施工项目承建所承包工程实际发生的各项生产费用的总和",{"key":23,"text":24,"correct":18},"D","指成本发生总额随着工程量的增减变动而成正比例变动的费用","固定成本是指在一定期间和一定的工程量范围内，成本额不受工程量增减变动的影响而相对固定的成本，如折旧费和管理人员的工资。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]