[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253834,838,1,"单选题","建立进度控制小组，将进度控制任务落实到个人属于施工项目进度控制措施中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","建立进度控制小组，将进度控制任务落实到个人属于施工项目进度控制措施中的组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]