[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253833,838,1,"单选题","理想的项目成本管理结果应该是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包成本>计划成本>实际成本",false,{"key":16,"text":17,"correct":18},"B","计划成本>承包成本>实际成本",true,{"key":20,"text":21,"correct":14},"C","计划成本>实际成本>承包成本",{"key":23,"text":24,"correct":14},"D","承包成本>实际成本>计划成本","理想的项目成本管理结果应该是计划成本>承包成本>实际成本。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]