[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253831":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253831,838,1,"单选题","施工项目成本计划是（ ）编制的项目经理部对项目施工成本进行计划管理的指导性文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工开始阶段",false,{"key":16,"text":17,"correct":18},"B","施工筹备阶段",true,{"key":20,"text":21,"correct":14},"C","施工准备阶段",{"key":23,"text":24,"correct":14},"D","施工进行阶段","施工项目成本计划是施工筹备阶段编制的项目经理部对项目施工成本进行计划管理的指导性文件。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]