[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253830":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":13},1253830,838,1,"单选题","某钢门窗安装工程，工程进行到第三个月末时，已完成工作预算费用40万元。完成工作实际费用为45万元，则该项目的成本控制效果是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用偏差为-5万元，项目运行超出预算",true,{"key":16,"text":17,"correct":18},"B","费用偏差为5万元，项目运行节支",false,{"key":20,"text":21,"correct":18},"C","费用偏差为5万元，项目运行超出预算",{"key":23,"text":24,"correct":18},"D","费用偏差为-5万元，项目运行节支",{"id":6,"name":26,"category":27,"favorite":28},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]