[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253829,838,1,"单选题","施工成本分类的方法，按成本发生的时间划分为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","抽象成本和实体成本",false,{"key":16,"text":17,"correct":14},"B","直接成本和间接成本",{"key":19,"text":20,"correct":21},"C","预算成本、计划成本和实际成本",true,{"key":23,"text":24,"correct":14},"D","固定成本和变动成本","施工成本分类的方法，按成本发生的时间划分预算成本、计划成本和实际成本。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]