[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253822,838,1,"单选题","某工程某月计划完成工程桩100根，计划单价为1.3万元\u002F根，实际完成工程桩110根，实际单价为1.4万元\u002F根，则费用偏差（CV）为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":14},"B","13",{"key":19,"text":20,"correct":14},"C","-13",{"key":22,"text":23,"correct":24},"D","-11",true,"费用偏差（CV）=-11万元",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]