[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253813,838,1,"单选题","下列关于施工成本控制的说法，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工成本控制应贯穿项目从投标开始到工程竣工验收的全过程",false,{"key":16,"text":17,"correct":18},"B","施工成本控制应对成本的形成过程进行分析，并寻求进一步降低成本的途径",true,{"key":20,"text":21,"correct":14},"C","施工成本控制需按动态控制原理对实际施工成本的发生过程进行有效控制",{"key":23,"text":24,"correct":14},"D","进度报告和工程变更及索赔资料是施工成本控制过程中的动态资料","施工成本分析是在施工成本核算的基础上，对成本的形成过程和影响成本升降的因素进行分析，以寻求进一步降低成本的途径。B答案错误",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]