[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253810,838,1,"单选题","施工成本控制过程中，为了及时发现施工成本是否超支，应该定期进行（ ）的比较。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工成本计划值与实际值",true,{"key":16,"text":17,"correct":18},"B","施工成本计划值与投标报价",false,{"key":20,"text":21,"correct":18},"C","成本实际值与投标报价",{"key":23,"text":24,"correct":18},"D","实际工程款支付与合同价","施工成本控制过程中，为了及时发现施工成本是否超支，应该定期进行施工成本计划值与实际值的比较。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]