[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253808,838,1,"单选题","施工项目目标成本的确定，人工、材料、机械的价格（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按市场价取定",true,{"key":16,"text":17,"correct":18},"B","按投标报价文件规定取定",false,{"key":20,"text":21,"correct":18},"C","按现行机械台班单价、周转设备租赁单价取定",{"key":23,"text":24,"correct":18},"D","按实际发生价取定","施工项目目标成本的确定，人工、材料、机械的价格按市场价取定。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]