[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253716":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253716,838,1,"单选题","隐蔽工程在隐蔽前应由（ ）通知有关单位进行验收，并形成验收文件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","施工单位",true,"隐蔽工程在隐蔽前应由施工单位通知有关单位进行验收，并形成验收文件。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]