[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253703,838,1,"单选题","交底时安全方面不包括（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","要在竖井每个门口设警戒标志，提醒安全作业不要跌入井道内",false,{"key":16,"text":17,"correct":14},"B","电缆盘的架设要稳固",{"key":19,"text":20,"correct":14},"C","核对每盘重量是否被施工升降梯所允许承载",{"key":22,"text":23,"correct":24},"D","电缆盘滚动搬运要平稳减速进行，防止碾压伤人",true,"交底时安全方面包括电缆竖井内作业要防止高空坠物，在电缆竖井未作隔堵前敷设电缆，要在竖井每个门口设警戒标志，提醒安全作业不要跌入井道内，电缆盘的架设要稳固，核对每盘重量是否被施工升降梯所允许承载，电缆盘滚动搬运要平稳匀速进行，防止碾压伤人等。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]