[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253675,838,1,"单选题","要明确技术交底的责任，责任人员不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目技术负责人",false,{"key":16,"text":17,"correct":18},"B","业主",true,{"key":20,"text":21,"correct":14},"C","作业队长",{"key":23,"text":24,"correct":14},"D","作业班组长","明确技术交底的责任。责任人员包括项目技术负责人、施工员、作业队长、作业班组长等。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]