[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253669,838,1,"单选题","案例一项目部在（ ）对工程质量进行了有效控制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","事前",false,{"key":16,"text":17,"correct":14},"B","事中",{"key":19,"text":20,"correct":14},"C","事后",{"key":22,"text":23,"correct":24},"D","事前、事中、事后三个阶段都",true,"项目部对工程质量控制各个阶段都有针对性的活动，自事前的编制施工组织设计、深化设计、人员上岗培训开始，到事中的材料遴选、管理人员加强巡视检查工程质量，最终把好检查验收关。说明项目部在事前、事中、事后三个阶段都对工程质量进行了有效控制。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]