[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253657,838,1,"单选题","正常调度的作用是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发现进度计划执行发生偏差先兆或已发生偏差，采用对生产资源分配进行调整",false,{"key":16,"text":17,"correct":14},"B","进入单位工程的生产资源是按进度计划供给的",{"key":19,"text":20,"correct":21},"C","按预期方案将资源在各专业间合理分配",true,{"key":23,"text":24,"correct":14},"D","消除进度偏差","正常调度是指进入单位工程的生产资源是按进度计划供给的，调度的作用是按预期方案将资源在各专业间合理分配。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]