[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253654,838,1,"单选题","下列有关施工进度计划与资源供给计划的关系叙述错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工进度计划编制前，必须对生产资源供给的状况和能力进行调查，做出评估，否则施工进度计划的实施有着一定的风险",false,{"key":16,"text":17,"correct":14},"B","施工进度计划确定后，是编制生产资源供给计划的依据，该计划的执行是施工进度计划实施的物质保证",{"key":19,"text":20,"correct":14},"C","施工进度计划的编制实行弹性原则，即计划要留有余地，使之有调整的可能",{"key":22,"text":23,"correct":24},"D","资源供给计划的编制好后，一般不宜调整",true,"施工进度计划的编制实行弹性原则，即计划要留有余地，使之有调整的可能。同样地，资源供给计划的编制也要坚持弹性原则，留有余地，当施工进度计划作出调整时使资源有可能进行调度。D答案错误",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]