[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253653,838,1,"单选题","施工进度是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","某项工作进行的速度",false,{"key":16,"text":17,"correct":18},"B","工程施工进行的速度",true,{"key":20,"text":21,"correct":14},"C","根据已批准的建设文件或签订的承发包合同，将工程项目的建设进度作出周密的安排，是把预期施工完成的工作按时间坐标序列表达出来的书面文件",{"key":23,"text":24,"correct":14},"D","工程从开工至竣工所经历的时间","施工进度是指在施工过程中各个工序的安排与时间顺序，以及各个工序的进度。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]