[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253652,838,1,"单选题","施工进度计划确定后，是（ ）的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工进度计划实施",false,{"key":16,"text":17,"correct":18},"B","编制生产资源供给计划",true,{"key":20,"text":21,"correct":14},"C","资源供给计划实施",{"key":23,"text":24,"correct":14},"D","编制资源管理计划","施工进度计划确定后，是编制生产资源供给计划的依据，该计划的执行是施工进度计划实施的物质保证。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]