[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253651,838,1,"单选题","施工进度计划是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","某项工作进行的速度",false,{"key":16,"text":17,"correct":14},"B","工程施工进行的速度",{"key":19,"text":20,"correct":21},"C","根据已批准的建设文件或签订的承发包合同，将工程项目的建设进度作出周密的安排，是把预期施工完成的工作按时间坐标序列表达出来的书面文件",true,{"key":23,"text":24,"correct":14},"D","工程从开工至竣工所经历的时间","施工进度计划是施工组织设计的关键内容，是控制工程施工进度和工程攻工期限等各项施工活动的依据，进度计划是否合理，直接影响施工速度、成本和质量。因此施工组织设计的切工作都要以施工进度为中心来安排。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]