[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253650,838,1,"单选题","案例一发生进度偏差的主要因素是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在项目内部，属于项目管理不当",true,{"key":16,"text":17,"correct":18},"B","作业队长不熟悉工艺要求造成的",false,{"key":20,"text":21,"correct":18},"C","项目外部的影响因素",{"key":23,"text":24,"correct":18},"D","供货商供货质量发生差异","案例一发生进度偏差的主要因素是在项目内部，属于项目管理不当。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]