[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253647,838,1,"单选题","依次施工的缺点是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由于同一工种工人无法连续施工造成窝工，从而使得施工工期较长",true,{"key":16,"text":17,"correct":18},"B","由于工作面拥挤，同时投人的人力、物力过多而造成组织困难和资源浪费",false,{"key":20,"text":21,"correct":18},"C","一种工人要对多个工序施工，使得熟练程度较低",{"key":23,"text":24,"correct":18},"D","容易在施工中遗漏某道工序","依次施工的缺点是由于同一工种工人无法连续施工造成窝工，从而使得施工工期较长。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]