[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253642,838,1,"单选题","所有施工对象的各施工段同时开工、同时完工的一种施工组织方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依次施工",false,{"key":16,"text":17,"correct":18},"B","平行施工",true,{"key":20,"text":21,"correct":14},"C","流水施工",{"key":23,"text":24,"correct":14},"D","不清楚","所有施工对象的各施工段同时开工、同时完工的一种施工组织方式是平行施工。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]