[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253634,838,1,"单选题","依据设计任务委托合同对设计工作进度的要求控制设计工作进度是（ ）进度控制的任务。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主方",false,{"key":16,"text":17,"correct":18},"B","设计方",true,{"key":20,"text":21,"correct":14},"C","施工方",{"key":23,"text":24,"correct":14},"D","供货方","依据设计任务委托合同对设计工作进度的要求控制设计工作进度是设计方进度控制的任务。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]