[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253631,838,1,"单选题","在调整施工进度计划时，采用实行包干激励，提高奖励金额；对所采取的技术措施给予相应的经济补偿是属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","经济措施",true,{"key":23,"text":24,"correct":14},"D","其他配套措施","进度控制的经济措施主要包括：1）对工期缩短给予奖励。2）对应急赶工给予优厚的赶工费。3）对拖延工期给予罚款、收赔偿金。4）提供资金、设备、材料和加工订货等供应保证措施。5）及时办理预付款及工程进度款支付手续。6）加强索赔管理。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]