[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253630,838,1,"单选题","应急调度是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进人单位工程的生产资源是按进度计划供给的",false,{"key":16,"text":17,"correct":18},"B","发现进度计划执行发生偏差先兆或已发生偏差，采用对生产资源分配进行调整，目的是消除进度偏差",true,{"key":20,"text":21,"correct":14},"C","检查计划执行效果的主要手段，可以发现进度有无偏差及偏差程度的大小",{"key":23,"text":24,"correct":14},"D","可以进一步协调各专业间的衔接关系，掌握工作面的状况和安全技术措施的落实程度，为下一轮计划的编制做好准备","应急调度是指发现进度计划执行发生偏差先兆或已发生偏差，采用对生产资源分配进行调整，目的是消除进度偏差。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]