[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253628,838,1,"单选题","能够充分合理地利用工作面争取时间，减少或避免工人停工、窝工，属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","依次施工",false,{"key":16,"text":17,"correct":14},"B","平行施工",{"key":19,"text":20,"correct":21},"C","流水施工",true,{"key":23,"text":24,"correct":14},"D","不清楚","流水施工能够充分合理地利用工作面争取时间，减少或避免工人停工、窝工。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]