[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253627,838,1,"单选题","能够直接、迅速和有效，但要注意其科学性，防止武断、主观和片面控制项目进度的方法属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","行政方法",true,{"key":16,"text":17,"correct":18},"B","经济方法",false,{"key":20,"text":21,"correct":18},"C","管理技术方法",{"key":23,"text":24,"correct":18},"D","其他方法","能够直接、迅速和有效，但要注意其科学性，防止武断、主观和片面控制项目进度的方法属于行政方法。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]