[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253626,838,1,"单选题","应急调度的目的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发现进度计划执行发生偏差先兆或已发生偏差，采用对生产资源分配进行调整",false,{"key":16,"text":17,"correct":14},"B","进入单位工程的生产资源是按进度计划供给的",{"key":19,"text":20,"correct":14},"C","按预期方案将资源在各专业间合理分配",{"key":22,"text":23,"correct":24},"D","消除进度偏差",true,"应急调度是指发现进度计划执行发生偏差先兆或已发生偏差，采用对生产资源分配进行调整，目的是消除进度偏差。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]