[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253622,838,1,"单选题","案例一这种影响进度计划实施的因素主要是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","供应商违约，违背采购合同对产品供应质量的约定",true,{"key":16,"text":17,"correct":18},"B","施工方造成的问题",false,{"key":20,"text":21,"correct":18},"C","自然因素导致施工延迟",{"key":23,"text":24,"correct":18},"D","供应商与施工方没有商议好","案例一这种影响进度计划实施的因素属于项目外部造成的，主要是供应商违约，违背采购合同对产品供应质量的约定。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]