[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253619,838,1,"单选题","甲公司中标一高级写字楼机电工程，内容含给水排水工程、通风与空调工程、电气工程等多个专业分部工程，由于工程量大、工期紧，需要编制施工进度网络计划，充分利用公司资源，进行严密组织施工，才能满足工期需要。根据背景资料，回答下列问题。 下列（ ）不是甲公司编制施工总进度网络计划的依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同工期的承诺",false,{"key":16,"text":17,"correct":14},"B","业主的项目建设计划",{"key":19,"text":20,"correct":14},"C","公司生产要素",{"key":22,"text":23,"correct":24},"D","监理单位实力",true,"监理单位实力不是甲公司编制施工总进度网络计划的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]