[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253616,838,1,"单选题","工程工期指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在平均建设管理水平、施工工艺和机械装备水平及正常的建设条件（自然的、社会经济的）下，工程从开工到竣工所经历的时间",false,{"key":16,"text":17,"correct":14},"B","根据项目方案具体的工艺、组织和管理等方面情况，排定网络计划后，根据网络计划所计算出的工期",{"key":19,"text":20,"correct":14},"C","指业主与承包商签订的合同中确定的承包商完成所承包项目的工期，也即业主对项目工期的期望",{"key":22,"text":23,"correct":24},"D","指工程从开工至竣工所经历的时间",true,"工程工期是指工程从开工至竣工所经历的时间，工程工期一般按日历日计算，有明确的起止年日。可以分为定额工期、计算工期与合同工期。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]