[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253614,838,1,"单选题","自由时差是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在不影响总工期的条件下，可以延误的最长时间",false,{"key":16,"text":17,"correct":18},"B","在不影响紧后工作最早开始时间的条件下，允许延误的最长时间",true,{"key":20,"text":21,"correct":14},"C","完成全部工作的时间",{"key":23,"text":24,"correct":14},"D","完成工作时间","自由时差是指在不影响紧后工作最早开始时间的条件下，允许延误的最长时间。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]