[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253612,838,1,"单选题","依据施工任务委托合同对施工进度的要求控制施工进度是（ ）进度控制的任务。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主方",false,{"key":16,"text":17,"correct":14},"B","设计方",{"key":19,"text":20,"correct":21},"C","施工方",true,{"key":23,"text":24,"correct":14},"D","供货方","依据施工任务委托合同对施工进度的要求控制施工进度是施工方进度控制的任务。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]