[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253611,838,1,"单选题","进度计划调整的方法不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","改变作业组织形式",false,{"key":16,"text":17,"correct":14},"B","在不违反工艺规律的情况下改变专业或工序衔接关系",{"key":19,"text":20,"correct":14},"C","修正施工方案",{"key":22,"text":23,"correct":24},"D","各专业分包单位不能如期履行分包合同",true,"进度计划调整的方法有：压缩或延长工作持续时间；增强或减弱资源供应强度；改变作业组织形式；在不违反工艺规律的情况下改变专业或工序衔接关系；修正施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]